LAHORE: Wapda and Power Construction Corporation of China have signed an agreement for installing 132kv transmission line from Duber Khwar Hydel Power Station to Dasu Hydropower Project, which would be completed in about eight months.
Dasu Hydropower General Manager Haji Muhammad Farooq and Power Construction Corporation China Business Development Manager Liu Zhong signed the agreement on behalf of their organisations.
The contract worth Rs1.583 billion includes procurement, design, supply, installation, stringing, testing and commissioning of 132kv single circuit transmission line from Duber Khwar to Dasu, and 132KV grid station at Dasu.