10,500MW projects in 4 years, 425MW Nandipur project to complete before June 30, Senate body told

byCustoms Today Report
20/02/2015
in Business
Share on FacebookShare on Twitter

Islamabad – The 425MW Nandipur Power Project would be fully operationalised before June 30 while a total of 10,500 MW projects would be completed in next 3-4 years, an official told the Senate Standing Committee on Water and Power.

It met here to review progress on Nandipur power plant, coal energy, Neelum Jehlum and Golan Gol transmission line projects.

You might also like

Dumpers Association rejects daily fuel price revision policy

23/07/2026

Petrol pump owners defer nationwide strike after negotiations with govt

22/07/2026

Nandipur Power Project MD M Mehmood told the body that three units of the plant had already been commissioned and the plant was being run on test. Currently, the plants were generating 300MW, he added.

Fourth unit of combine circle would be ready before June 30 and the plant would supply 425 MW electricity to the national grid system, he said. He added earlier fuel treatment plant was not working now it was fully functional.

He said all projects would be completed in phases including Gaddani power projects and currently the government has focused on short term projects having 10,500 MW which would be completed in next 3-4 years. He said that all coal based power projects were being set up by the private sector.

He said that three coal based power plants would be set up during the 1st phase in the country adding that these would be run on local coal. One plant of 300 MW would be set up in Salt Range (Punjab) while two plants of 1320 MW and 660 MW would be established in Thar Block-1 and Thar Block-2 respectively.

Related Stories

Dumpers Association rejects daily fuel price revision policy

byCT Report
23/07/2026

KARACHI: The Dumpers Association has rejected the government’s proposed plan to revise petroleum product prices on a daily basis, warning...

Petrol pump owners defer nationwide strike after negotiations with govt

byCT Report
22/07/2026

ISLAMABAD: The All Pakistan Petrol Pumps Owners Association (APPPOA) on Wednesday postponed its planned nationwide strike after successful negotiations with...

FBR excludes FTA, PTA customs concessions from 2026 tax expenditure report

byCT Report
21/07/2026

ISLAMABAD: The Federal Board of Revenue (FBR) has left customs duty concessions granted under Free Trade Agreements (FTAs) and Preferential...

Pakistan starts daily petrol, diesel updates from today

byCT Report
20/07/2026

ISLAMABAD: Pakistan has introduced a new daily pricing mechanism for petroleum products, replacing the previous periodic revision system. Under the...

Next Post

$2.6 billion trade: Qaim for increasing economic ties with Germany

  • Terms and Conditions
  • Disclaimer

© 2011 Customs Today -World's first newspaper on customs. Customs Today.

No Result
View All Result
  • Transfers and Postings
  • Latest News
  • Karachi
  • Islamabad
  • Lahore
  • National
  • Chambers & Associations
  • Business
  • About Us

© 2011 Customs Today -World's first newspaper on customs. Customs Today.