Home Breaking News

Neelum-Jhelum hydropower project suffers damage worth Rs22.5bn after tunnel collapse

byCT Report
22/11/2022
in Breaking News, Business, Latest News, Slider News
Share on FacebookShare on Twitter

ISLAMABAD: The 969 MW Neelum-Jhelum hydropower project, which is non-operational since July 6, in the wake of blockage that appeared in the 3.5km Tail Race Tunnel (TRT), has seen an estimated damage of Rs22.50 billion (Rs2.50 billion construction cost and Rs20 billion as business loss).

“The project will now come on stream by the end of February 2023. Till February 2023, the project would brave a business loss of Rs20 billion,” a senior official of the Neelum-Jhelum Hydropower Company Limited (NJHPCL) told media.

You might also like

PIAF welcomes Rs200b tariff relief, calls for comprehensive industrial reforms

01/06/2026

FBR recovers Rs4m from Cheezious in tax compliance action

01/06/2026

When asked as to who will bear the loss, either the government or NICL (National Insurance Company Limited), the official said that both the heads, TRT, and business loss, are covered under the insurance agreement, so Wapda will not bear the loss.

“NICL has a 7% share and a group of Chinese companies 93% in the insurance amount. And they will share the cost to be incurred on making the project operational.”

The official said since the CoD of the project ie April 2018, the insurance company is getting Rs1 billion from NJHPCL and so far, Rs4 billion have been received by the insurance company. Now they will pay the damage cost of Rs2.5 billion and a business loss of Rs20 billion.

The person said the Neelum-Jhelum hydropower project generates business of Rs48-50 billion.

“In three months of the summer season, four units (turbines) of the project become operational, in six months, three units and in three months of winter only one unit runs depending on flows of water.”

The official said that authorities have decided to purchase the maintenance vehicle for the inspection of the tunnel and complete the construction of the tunnel as soon as possible.

The initial report about the tunnel debacle suggests that on July 4, when the plant was running at its full capacity (969MW), an abnormal increase in water leakage was observed in the powerhouse, which was controlled through continuous drainage pumps.

Upon investigation, high water pressure in the TRT was observed. Accordingly, on July 5, it was concluded by the project consultants that an abnormal increase in TRT pressure and water leakages/seepage in the powerhouse are due to blockage in TRT.

Considering the safety of the power structure and all other equipment/machinery, units were shut down gradually. As a result, the powerhouse was shut down on July 6.

Immediately after this incident, China Gezhouba Group Company (CGGC), the contractor for the construction of civil works, was engaged in carrying out remedial works.

The firm immediately reached the site and a contract agreement was signed with it on August 5, and the work commenced on August 27.

The Neelum-Jhelum hydropower project was executed at the cost of Rs430 billion and it started functioning in April 2018 under the deep mountains in the AJK where the geology is neither predictable nor readable.

Related Stories

PIAF welcomes Rs200b tariff relief, calls for comprehensive industrial reforms

byCT Report
01/06/2026

LAHORE: The Pakistan Industrial and Traders Associations Front (PIAF) has welcomed the government’s decision to provide approximately Rs200 billion in...

FBR recovers Rs4m from Cheezious in tax compliance action

byCT Report
01/06/2026

SAHIWAL: The Federal Board of Revenue (FBR) has recovered Rs. 4 million from popular fast-food chain Cheezious following an enforcement...

FBR revenue shortfall swells to Rs868b as tax collection misses target

byCT Report
01/06/2026

ISLAMABAD: The Federal Board of Revenue (FBR) recorded a revenue gap of Rs868 billion during the first 11 months of...

Pakistan likely to allocate Rs1,126b for development projects in budget 2026-27

byCT Report
01/06/2026

ISLAMABAD: Pakistan is expected to allocate around Rs1,126 billion for development projects in the upcoming federal budget 2026–27, according to...

Next Post

ICCI, ICSTSI call for promoting ease of doing business

  • Terms and Conditions
  • Disclaimer

© 2011 Customs Today -World's first newspaper on customs. Customs Today.

No Result
View All Result
  • Transfers and Postings
  • Latest News
  • Karachi
  • Islamabad
  • Lahore
  • National
  • Chambers & Associations
  • Business
  • About Us

© 2011 Customs Today -World's first newspaper on customs. Customs Today.