Wapda tests all three units of Tarbela 4th Extension Project

byCT Report
24/11/2018
in Business
Share on FacebookShare on Twitter

ISLAMABAD: The Pakistan Water and Power Development Authority (WAPDA) has successfully carried out simultaneous load rejection test of all three units of Tarbela 4th Extension Hydropower Project.

The test was conducted at a load of about 1,100 Megawatts (MW) under the supervision of the consultants and the contractor of the project.

You might also like

Govt to build 500MW floating solar project at Keenjhar Lake

08/05/2026

Electricity consumers likely to receive Rs63.94bn relief

07/05/2026

The simultaneous load rejection test was aimed at testing the stability of underwater parts and rise in speed and pressure of the turbines. Simultaneous load rejection test is carried out once a hydropower project is complete and it’s generating units are fully operational.

Turbine efficiency test was also carried out last week under the supervision of an international expert who was hired specifically for the purpose. The test ascertained that the turbine efficiency was more than the efficiency envisaged during the model testing of the turbines.

The completion of Tarbela 4th Extension and Neelum Jhelum hydropower projects this year has exerted a positive impact on the overall hydel generation, as it surged to 5,241MW during the peak hours on Friday, registering an increase of about 46 per cent as compared to 3,581MW generated on the same day last year.

Since its commissioning, Tarbela 4th Extension Hydropower Project has so far contributed 1.26 billion units of low-cost hydel electricity to the national grid despite low flows of water this year.

The 1,410MW-Tarbela 4th Extension Hydropower Project has been constructed on tunnel no. 4 of Tarbela Dam. The project has three generating units, each of them having a capacity of 470MW. The project will provide 3.84 billion units of electricity on the average to the national grid per annum. Annual benefits of the project have been estimated at Rs30 billion.

Related Stories

Govt to build 500MW floating solar project at Keenjhar Lake

byCT Report
08/05/2026

KARACHI: The government has planned a 500-megawatt floating solar power project at Keenjhar Lake in Sindh with an estimated cost...

Electricity consumers likely to receive Rs63.94bn relief

byCT Report
07/05/2026

ISLAMABAD: Electricity consumers across the country, including those served by K-Electric, may receive relief of up to Rs63.94 billion under...

Govt introduces public-driven model for area development projects

byCT Report
06/05/2026

ISLAMABAD: Now citizens have been given the right to suggest development schemes for their areas. As per new guidelines issued...

Punjab revises property valuation rates to attract UAE & Gulf investors

byCT Report
05/05/2026

LAHORE: The Punjab government has started revising property valuation rates across multiple districts in an effort to attract foreign investment,...

Next Post

Egypt Recovers 26 Ancient Artifacts From Switzerland

  • Terms and Conditions
  • Disclaimer

© 2011 Customs Today -World's first newspaper on customs. Customs Today.

No Result
View All Result
  • Transfers and Postings
  • Latest News
  • Karachi
  • Islamabad
  • Lahore
  • National
  • Chambers & Associations
  • Business
  • About Us

© 2011 Customs Today -World's first newspaper on customs. Customs Today.